SynchroGrid developed new settings for relays located at Corinth, Sycamore Creek, Garland & Stanton substations.
The process involved the following:
SynchroGrid provided relay settings and GOOSE messaging review along with quality control for Cross Texas Transmission's Railhead reactor additions.
SynchroGrid provided relay settings and GOOSE messaging review along with quality control for Cross Texas Transmission's Gray to Allen Creek line additions.
SynchroGrid provided relay settings and GOOSE messaging review along with quality control for Cross Texas Transmission's Gray shunt reactor upgrades.
SynchroGrid provided an analysis of the operation of a 345kV bus trip.
SynchroGrid provided relay settings services for the entire 138:12.47kV Substation.
SynchroGrid developed relay settings for transformer protection, bus protection, and feeder protection at Oncor Electric’s West Texas Gulf Substation. Relay coordination was also provided for the transformer and distribution feeder.
SynchroGrid provided relay setting and relay coordination services for Oncor Electric's Midessa Substation.
SynchroGrid provided relay setting development services for Oncor Electric at their Glenhaven Substation.
SynchroGrid developed extensive relay settings for Oncor Electric's Cowden North Substation. In addition, we provided relay coordination for the transformer and distribution feeder.
SynchroGrid developed extensive relay settings as well as relay coordination for Oncor Electric's Alkali Lake Substation.
SynchroGrid developed relay settings for transformer protection, bus protection, feeder protection and bus tie protection at Oncor Electric’s Cheyenne Substation. Relay coordination was also provided for the transformer and distribution feeder.
SynchroGrid developed relay settings for transformer protection, bus protection, and feeder protection at Oncor Electric’s Barstow Northwest Substation. Relay coordination was also provided for the transformer and distribution feeder.
SynchroGrid upgraded SEL 487E-0 Reactor relays with SEL-487E-3 relays.
SynchroGrid replaced GE-T60 reactor relays with SEL-387E relays and upgraded SEL 487E-0 reactor relays with SEL-487E-3 relays.
SynchroGrid provided a relay settings review for the ERCOT Region. This was for ERCOT RARF 5.4.
SynchroGrid provided relay setting and relay coordination services for Oncor Electric's Midessa Substation.
SynchroGrid provided relay setting development services for Oncor Electric's Shipwreck Substation.
SynchroGrid performed an arc flash analysis on the electrical distribution system for South Kent Wind Farm - a wind farm operated by Pattern Energy.
SynchroGrid performed an arc flash analysis on the electrical distribution system for a wind farm operated by Pattern Energy.
SynchroGrid developed relay settings and provided relay coordination services for Oncor Electric's Odessa Southwest Substations.
SynchroGrid provided relay setting development and coordination services for Oncor Electric’s Castile Hills Substation.
SynchroGrid provided relay setting development services for Oncor Electric's International Airport Substation.
SynchroGrid provided relay settings for Oncor Electric's McLennan County East Substation.
SynchroGrid provided quality system protection services in developing settings for a number of local terminals including Enterprise, TAMU, and Dowling terminals.
This project consisted of verifying the adequacy and reliability of new features and settings along with existing settings within the firmware upgrade.
SynchroGrid provided relay setting and relay coordination services for Oncor Electric's Horsehead Draw Substation.